Kelly Phase I

PROJECT SCOPE:

Phase I:

  • Building A - Kitchen, Library and STEAM Lab

    • New servery addition 

    • Modernization of student restrooms

  • Building B - Administration Building

    • Low voltage infrastructure upgrades

  • Building C - Kindergarten

    • New technology, finishes and casework

  • Building D, E and F - Existing Classroom Buildings

    • New technology, finishes and casework

  • Building G - New Multipurpose Building  

    • New construction of a multi-purpose building and lunch shelter

  • Relocatable Buildings - Existing Classrooms

    • New technology, finishes and casework

  • Campus Wide Upgrades 

    • Mechanical, electrical and plumbing system upgrades

    • New keyless entry door system

  • Site Work - 

    • Installation of two new playgrounds

    • New blacktop play area

    • New bio-retention planters

Phase II - 

  • Completion of the Storm Water and Grading Permit

  • Lighting, ceiling and low voltage upgrades in existing classrooms

  • Door hardware and access controls at existing doors

  • New exterior paint 

  • Existing playground upgrades 

BUDGET:

Phase I -  $17M

Phase II - Estimate $5.5M

PROJECT STATUS:

Phase I - 100% Complete. Division of State Architect (DSA) certification pending. 

Phase II - In design. Construction starts Summer of 2023.