PROJECT SCOPE:
Phase I:
Building A - Admin, Library and MPR
Alteration of and addition to the existing building
Building B - Existing Kindergarten
New lighting, finishes and casework
Building K - New Kindergarten
Two new kindergarten classrooms with new restrooms and support spaces
Building G and H - New Classrooms
Four new upper-grade classroom buildings with new restrooms and support spaces
Building J - New Classrooms and New STEAM Lab
Two new upper-grade classrooms with new restrooms and support spaces
New STEAM Lab
Building B, C, D, E and F -
Replacement of acoustical ceilings, lighting, fire alarm, new exterior door hardware, roof replacement and new exterior siding
Relocatable Buildings -
New lighting, finishes and casework
Campus Wide Upgrades -
Mechanical, electrical and plumbing system upgrades
New keyless entry door system
Site Work -
New kindergarten shade structure
Installation of new play equipment at the kindergarten and primary grounds and landscaping
Removal of 10 portable buildings and 1 toilet building
Phase II -
Completion of the Storm Water and Grading Permit
Installation of the lunch shelter
Completion of the blacktop play area
BUDGET:
Phase I - $21M
Phase II - Estimate $3.0M
PROJECT STATUS:
Phase I - 100% Complete. Division of State Architect (DSA) certification pending.
Phase II - In design. Construction starts Summer of 2023.
PRESENTATIONS: All Phase 1 Presentations